16 Feb 2021 - Arrived at location on banks of Lake Victoria where CIP plant were to be built on Mine Permit19 Feb 2021 - Legalities with land owner finalized20 Feb 2021 - Community consultations initiated21 Feb 2021 - Site cleared and ready for construction of CIP plant24 Feb 2021 - Construction of roads to give access for vehicles and trucks8 March 2021 - Structures going up19 March 2021 - First building complete. Security gates and fencing complete.20 March 2021 - Sharing our lunch from temporary field kitchen29 March 2021 - Training of security personnel selected from local community1 April 2021 - First heavy equipment arriving28 March 2021 - Preparing for construction of CIP plant foundation9 April 2021 - Platform construction continues11 May 2021 - Platform near completion28 July 2021 - Plant components arrive at site4 August 2021 - Construction of CIP plant starts16 August 2021 - Leach tanks under constructions16 August 2021 - Water pumps and pipes being installed to supply water to plant (850m length and 25m head)27 August 2021 - Thickener tank construction starts1 September 2021 - Construction of crushing circuit foundations initiated9 September 2021 - Agitator housing going up14 September 2021 - Filter press machines getting lifted into placeWorking through night28 September 2021 - Ponds under construction1 October 2021 - Constructing the plant walk ways1 October 2021 - Pond construction and lining complete. First water flow from the lake13 September 2021 - Ballmill getting prepared for commissioning process2 October 2021 - Cyclones and piping getting installed5 October 2021 - All ponds, laboratory and warehouse complete and operational10 November 2021 - Plant commissioning starts17 November 2021 - First gold produced