KENYA 16 Feb 2021 - Arrived at location on banks of Lake Victoria where CIP plant were to be built on Mine Permit 19 Feb 2021 - Legalities with land owner finalized 20 Feb 2021 - Community consultations initiated 21 Feb 2021 - Site cleared and ready for construction of CIP plant 24 Feb 2021 - Construction of roads to give access for vehicles and trucks 8 March 2021 - Structures going up 19 March 2021 - First building complete. Security gates and fencing complete. 20 March 2021 - Sharing our lunch from temporary field kitchen 29 March 2021 - Training of security personnel selected from local community 1 April 2021 - First heavy equipment arriving 28 March 2021 - Preparing for construction of CIP plant foundation 9 April 2021 - Platform construction continues 11 May 2021 - Platform near completion 28 July 2021 - Plant components arrive at site 4 August 2021 - Construction of CIP plant starts 16 August 2021 - Leach tanks under constructions 16 August 2021 - Water pumps and pipes being installed to supply water to plant (850m length and 25m head) 27 August 2021 - Thickener tank construction starts 1 September 2021 - Construction of crushing circuit foundations initiated 9 September 2021 - Agitator housing going up 14 September 2021 - Filter press machines getting lifted into place Working through night 28 September 2021 - Ponds under construction 1 October 2021 - Constructing the plant walk ways 1 October 2021 - Pond construction and lining complete. First water flow from the lake 13 September 2021 - Ballmill getting prepared for commissioning process 2 October 2021 - Cyclones and piping getting installed 5 October 2021 - All ponds, laboratory and warehouse complete and operational 10 November 2021 - Plant commissioning starts 17 November 2021 - First gold produced