KENYA

16 Feb 2021 - Arrived at location on banks of Lake Victoria where CIP plant were to be built on Mine Permit

19 Feb 2021 - Legalities with land owner finalized

20 Feb 2021 - Community consultations initiated

21 Feb 2021 - Site cleared and ready for construction of CIP plant

24 Feb 2021 - Construction of roads to give access for vehicles and trucks

8 March 2021 - Structures going up



19 March 2021 - First building complete. Security gates and fencing complete.

20 March 2021 - Sharing our lunch from temporary field kitchen


29 March 2021 - Training of security personnel selected from local community

1 April 2021 - First heavy equipment arriving


28 March 2021 - Preparing for construction of CIP plant foundation


9 April 2021 - Platform construction continues



11 May 2021 - Platform near completion

28 July 2021 - Plant components arrive at site


4 August 2021 - Construction of CIP plant starts

16 August 2021 - Leach tanks under constructions

16 August 2021 - Water pumps and pipes being installed to supply water to plant (850m length and 25m head)

27 August 2021 - Thickener tank construction starts


1 September 2021 - Construction of crushing circuit foundations initiated


9 September 2021 - Agitator housing going up



14 September 2021 - Filter press machines getting lifted into place






Working through night

28 September 2021 - Ponds under construction

1 October 2021 - Constructing the plant walk ways

1 October 2021 - Pond construction and lining complete. First water flow from the lake

13 September 2021 - Ballmill getting prepared for commissioning process

2 October 2021 - Cyclones and piping getting installed

5 October 2021 - All ponds, laboratory and warehouse complete and operational

10 November 2021 - Plant commissioning starts




17 November 2021 - First gold produced




